Difference between revisions of "Filth"
m |
m (→Rough task list, to be refined) |
||
Line 52: | Line 52: | ||
** Hand tools from tool board and/or office drawer block | ** Hand tools from tool board and/or office drawer block | ||
* Put everything that remains back in | * Put everything that remains back in | ||
+ | |||
+ | ===Optional, perhaps outside of the scope of this project=== | ||
+ | |||
+ | * Split toolboard up into soldering tools and other, move soldering tools west. | ||
+ | * Create tables or [......] in front of the windows now that that becomes unoccupied | ||
+ | * Reroute/replace UTP to new location of core switch(es) (glass room? or not?) | ||
+ | * Perhaps relocate audio mixer to more central place (if so desired) |
Revision as of 15:58, 25 August 2014
Contents
Operation FILTH
or, How to inflate our dirty room to 200%
Date/Period:
Unknown, not set yet, to be determined
Participants/volunteers:
(if for a specific part, please indicate that behind your name):
Rough task list, to be refined
- Relocate remaining network equipment outside, well shielded from dust(!!)
- Take just about everything out of the rooms, store intelligently. Dustproof the rest.
- Make sure the high tables in front of the window are not blocked by that stuff
- Take out the parts of the ceiling tiles and supports that will interfere with our work
- Take out the air conduits that risk getting pierced/damaged by flying debris.
- Tape dustproof/watertight everything that needs protecting, like the fusebox and...
- Disconnect the electricity outlet+cable that is inside the wall we're taking down.
- Tape the door+doorframe so dust is contained inside rooms as well as can be
- Arrange for protective wear: dust masks, eyewear, ear protection, builders' helmets...
- Break wall down (with what, possibly rent tool?)
- Dispose of the debris. Inquire what (if any) possibilities exist at UR
- Plaster/fixup walls where needed. Paint 'em too?
- Clean everything up well
- Where needed, egalize floor so it can support laminate
- Put in laminate floor, wall to wall
- Remove wood from door bottom to accomodate new floor
- Design/purchase/build a (rubber?) dustproof strip to put on door.
- Rearrange ceiling slats so the ceiling will be seamless
- Cut ceiling tiles to match, where needed
- Block off one door, (possibly using extra insulation?)
- Build and secure the benches using the high tables as frames + Gamma plywood
- Paint/varnish the benches (perhaps??)
- Put some powertools in, where appropriate, like on walls or on dedicated platforms.
- Put sink in, drill through wall to kitchen, arrange water conduits
- Redo/expand/fix electricity. People have expressed desire for emergency cut-off switch
- Arrange storage space for:
- Wood; sheets
- Wood; scrap pieces
- Wood, metal, plastic; lengthy stuff like rods, pipes, sticks, etc
- Wood, perhaps metal; large beams
- Metal; scraps and small sheets
- Power tool storage off the benches
- Screws, plugs, bolts; re-hang red drawers etc
- Hand tools from tool board and/or office drawer block
- Put everything that remains back in
Optional, perhaps outside of the scope of this project
- Split toolboard up into soldering tools and other, move soldering tools west.
- Create tables or [......] in front of the windows now that that becomes unoccupied
- Reroute/replace UTP to new location of core switch(es) (glass room? or not?)
- Perhaps relocate audio mixer to more central place (if so desired)