Difference between revisions of "Cerberus (metric)"

From Technologia Incognita
Jump to: navigation, search
m
 
(22 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
{{Project
 
{{Project
 
|ProjectSkills=Electronics, Fine mechanics, Assembling, Construction,
 
|ProjectSkills=Electronics, Fine mechanics, Assembling, Construction,
|ProjectStatus=Planning
+
|ProjectStatus=Finished
 
|ProjectNiche=Mechanics
 
|ProjectNiche=Mechanics
 
|ProjectPurpose=World domination
 
|ProjectPurpose=World domination
Line 27: Line 27:
  
 
* I, Ultratux, will probably build one as well, even though I have the earlier adapted variant.
 
* I, Ultratux, will probably build one as well, even though I have the earlier adapted variant.
* Damnlie has shown interest
+
* <s>Damnlie has shown interest</s> but had to cancel
* rad0 will very likely build one and volunteered to documment the whole process.
+
* rad0 will build one and volunteered to document the whole process.
* caduceus has shown interest
+
* <s>caduceus has shown interest</s> but cancelled / doesn't reply to emails
 +
* rep will participate
 +
* <s>jeroen has shown interest, but only in the delta robot, not the printing part</s>
 +
* <s>milo has shown interest but isn't sure yet</s>
 +
* Mattronix will participate
  
= Proposed timeline =
+
= Cost / Budget estimation =
  
Without the parts from Grabercars, this project cannot take off. So first, I will wait for his reply and/or seek contact again by different means. Hopefully he'll reply with good news and we can order the parts.<br>
+
Here is an educated guess of what all the parts needed will cost, per printer...
Then, I plan to take the order for the aluminum extrusions, so I need to know the length everyone desires. Standard is 1000mm. I prefer ordering them cut, they can make much nicer cuts than we can, but mostly it helps with shipping; because 6 meter lenghts don't come by DHL...<br>
+
 
In the mean time, a start should have been made with printing many of the base parts as shown in the pic. For 4 printers, we'd need 48 such parts, (plus a number of smaller parts)<br>
+
4x stepper motors NEMA17:                          55
 +
Controller board (Minitronics):                    79
 +
Heated bed square PCB:                              23
 +
Mk-7 filament drive gear:                            6
 +
3x aluminum extrusions 1000mm                      60
 +
 +
Bowden version of E3D Hotend:                      70
 +
(calculated as £55 == 64 euro plus shipping...)
 +
 +
Drive reels and rollers by Grabercars             100
 +
(calculated as 118 US$ = 87 euro, minus discount, plus shipping, plus customs)
 +
 +
Printed parts                                      30
 +
(calculated as ~1kg per printer=22 euros. Plus electricity, plus failed prints...)
 +
 +
Round hardened glass bed 30cm (Blokker)              9
 +
Aluminum actuator arms                              6
 +
Aluminum rods ("frame bracing")                    12
 +
Power supply                                     20
 +
Spectra fishing filament                            5
 +
Magnets and balls or ball joints, estimated        20
 +
Different types of glue, heat-resistant and other  15
 +
 +
Misc: bolts, screws, microswitches, wiring,
 +
  fans, connectors, all little stuff I forgot...    40
 +
 +
Grand total:                                      550
 +
 
 +
It should be well understood that changing or adding options like carbon fibre arms, different controllers, more hotends, different dimensions etc will drive the price up. But to the best of my knowledge, this bill of materials is complete for building a working complete printer, without compromising.
 +
 
 +
Please also note I did my best to estimate shipping and other fees correctly, but I cannot guarantee this will be 100% accurate. Maybe allow for a safety margin.
 +
 
 +
= Timeline =
 +
 
 +
I plan to place the order for the aluminum extrusions by Thursday November 7th, so I need to know the length everyone desires. Standard is 1000mm. I prefer ordering them cut, they can make much nicer cuts than we can, but mostly it helps with shipping; because 6 meter lenghts don't come by DHL...<br>
 +
In the mean time, a start should have been made with printing many of the base parts as shown in the pic. For 4 printers, we'd need 48 such parts, (plus a number of smaller parts). However, it has transpired that we need to have the aluminum extrusions to ascertain a good fit, before printing all parts.<br>
 
Then to assemble and thread the towers, the only part(s) missing are the stepper motors. So by this time, we can either order the stepper motors, the stepper motors plus controller boards, or even ALL the remaining parts (extruder parts, hotends, heatbed etc.) So there is time until this step to choose hotend options, controller options, etc.
 
Then to assemble and thread the towers, the only part(s) missing are the stepper motors. So by this time, we can either order the stepper motors, the stepper motors plus controller boards, or even ALL the remaining parts (extruder parts, hotends, heatbed etc.) So there is time until this step to choose hotend options, controller options, etc.
 
<br>
 
<br>
 +
 +
Nov 12, 2013: ordered 4 sets of aluminum extrusions, 1000mm
 +
Nov 13, 2013: ordered a big quantity of thermal glue off DX to save some money...
 +
Nov 18, 2013: ordered steel balls 10mm
 +
Nov 20, 2013: ordered a heap of filament and a few stepper motors and controllers
 +
Nov 23, 2013: ordered countersunk magnets via ebay...
 +
Nov 24, 2013: finalize order from grabercars
  
 
=Testing the first printed parts=
 
=Testing the first printed parts=
Line 44: Line 90:
 
[[File:20131011 232157.jpg|240px]]
 
[[File:20131011 232157.jpg|240px]]
  
=Better implementation of bowden connection=
+
=Better HotEnd=
 +
 
 +
While looking for a solution to my ongoing extruder/hotend problems (it has skipping issues probably due to clogging) I at first wanted to purchase a better bowden connector with a pneufit, but soon after stumbled onto a modern and smart hotend design by E3D which offers a number of very clear advantages over my current J-Head;
 +
* Can sustain ''much'' higher temperatures because it has no PEEK or PTFE parts. Like over 300. Or even over 400.
 +
* Has no PTFE parts that can deteriorate, swell, leak, pinch or crush the filament, so probably more reliable.
 +
* Has instead of a power resistor a ceramic element which heats up extremely much faster.
 +
* Has a channeled fan casing/duct so the cooling isn't accomplished by accident, but with degrees of certainty.
 +
 
 +
And as far as I can see now, has just one drawback:
 +
* Has a mechanical weak point, so a head crash into the bed or something similar is ''really'' to be avoided at all cost.
 +
 
 +
I have been working on mounting it today but there was too much else to do plus my pneufit coupling went missing so that got delayed. And I need to adapt the holder because it doesn't fit this one as-is. And after that I need to change settings in firmware and in slic3r, and recalibrate the Z. But when done, I ought to have a better hotend which also has a much stronger pneufit bowden connector, which therefore permits the use of a stronger stepper motor, allowing higher feed rates thus feeding filament faster in a reliable way, which eventually will result in finally attaining the higher speeds these delta printers ought to be able to sustain (the platform being so lightweight). I hate it that I needed to severely limit my speed due to the extruder not being able to keep up. So I am very excited by this...
 +
 
 +
Sadly, my time is very limited this week due to personal reasons. Stay tuned for news later!
 +
<br>
 +
...<br>
 +
<br>
 +
To cut a long story short: the new hotend is '''Fan-effing-tastic'''. Not only have all my extruder problems disappeared, but I was able to increase print speeds 220% (from 50 to 110) and as a bonus, I see no more stringing, as if by magic. This is the best return-on-investment I could ever have hoped for.
 +
 
 +
=Small problem / minor setback=
 +
 
 +
For my first printer I searched many shops to find a suitable round cheap glass bed. This proved rather hard to find. I finally got lucky in a Blokker store which sells a 30cm glass turntable for food serving purposes. Hardened glass, smooth edge, cheap: perfect. I bought two.. One spare.
 +
Now, I need to find a bunch more but... they no longer carry them. I visited 4 shops yesterday to no avail. Today, one which -upon inquiry with the manager- turned up two, stocked far away in the 'basement'. <s>So, '''IF''' you happen to stumble onto one of these, do not hesitate and buy ! As of today, we need 2-3 more still...</s> Update: I managed to get my hands on 3 more, so this has been addressed. <br>
 +
 
 +
=Extrusion profile=
 +
 
 +
A week ago I found out the STL files of the parts that ought to fit 'around' the aluminum extrusions, didn't fit my current extrusions. I started looking into ways to change the STL files or find a different source for the extrusions. This proved hard, many vendors don't carry it, are unclear whether they carry it, or had extrusion profiles that were incompatible too, for various reasons.
 +
In the end however, I found out that my original source carries two variants of the 40x40 profile, and the second, thicker, heavier one does seem to fit our STL files... somewhat unexpectedly. So this ought to be fixed already. I've meticulously checked overlayed printouts of both items, and I feel confident it will fit inside. Otherwise, we could always still do some adjustments on the OpenSCAD files.
 +
 
 +
=Big update=
 +
 
 +
I wasn't happy with the prints we did; once the extrusions were there, we found that the braces need serious filing in the corners.  I opted to adjust the corner radius in openscad, that ought to help. Secondly, the three tripods should fit together much easier, I also saw tolerances there that were unacceptable. I tried to recalibrate the slicer to make those errors diminish or disappear. We'll have to see.
 +
 
 +
Also, I finalized the number of participants, therefore the bill of materials. We started to order the first few things, either because time constraints force me to, or because we simply need them to proceed.
 +
 
 +
I had skipping or slipping in my left tower which destroyed a lot of prints, usually 80% through. This was getting to be a real problem; I managed to avoid this problem by bringing the speed down from 120 mm/s to 90 mm/s. But it merits future attention.
 +
At least now, the printer prints reliably again.
  
For my current printer, I have made an intricate hinge to push the bowden into the hotend. However, today I found out that a pressfit adapter feeding the PTFE ''through'' exists, see [[http://reprap.me/WebRoot/StoreDK/Shops/reprap_nu_4149051/5034/ABD3/3E4F/E712/E513/5DA7/BC05/3E55/1.jpg]] and [[http://reprap.me/WebRoot/StoreDK/Shops/reprap_nu_4149051/5034/ABD3/3E4F/E712/E513/5DA7/BC05/3E55/3.jpg]]. This makes for a much stronger connection, which therefore permits the use of a stronger stepper motor, allowing higher feed rates thus feeding filament faster in a reliable way, which eventually will result in finally attaining the higher speeds these delta printers ought to be able to sustain (the platform being so lightweight). I hate it that I needed to severely limit my speed due to the extruder not being able to keep up. So I am very excited by this... I need me to order one ASAP!
+
Having done some reading and research I felt the necessity to go for magnet-ball joints, so I ordered the magnets and balls. The shipping of such items can take many weeks, so I hope delays won't get too bad. We have as yet to find (or design) carriages and an actuator/platform that will fit those, but I feel confident that can be found, adapted or designed.

Latest revision as of 22:42, 14 July 2015

Projects
Participants Ultratux
Skills Electronics, Fine mechanics, Assembling, Construction
Status Finished
Niche Mechanics
Purpose World domination

Workshop aiming to build a number of 3D printers of the "delta robot" principle. We will try to stick to the original design as much as possible, but with metric/EU parts.

First steps

  • Waiting to see how many participants will join, to know in which numbers to order components
  • Querying wishes of participants in regards to build volume, other details, etc.
  • Compiling a bill of materials and defining correct order to purchase them in
  • Making sure all parts can be acquired in a timely fashion (and for a fair price)
  • Printing a few of the parts, noting time required and quality/checking tolerances
  • Scheduling a first pre-purchase planning meeting?

I've built my first printer with 1 meter aluminum extrusions, but a bit higher or lower is also possible. Say minimum ~75cm, max ~1m20 maybe ? It would be good to hear everyone's preference to get the order of that under way.

I've emailed Steve Graber, waiting to hear back from him on availability and cost of the CNC'ed parts...

Yesterday I have printed three parts -see pic-. The two upper parts each took 3,5 hours to print. The lower one took 3 hours. The two upper parts are supposed to fit together, but it is extremely tight, I need to test if it fits or that printing adjustments need to be made (or machining...) Also, whether the lower part fits my extrusion profile which is hard to test without disassembling my printer..
20131010 024607.jpg

Then, as each printer needs six pcs of each pictured part (not 100% identical but close enough) this means 40 hours of printing(!) for just the base building blocks for 1 printer. This means careful planning is in order to avoid disappointments, and perhaps an early start on printing objects.

Participants

  • I, Ultratux, will probably build one as well, even though I have the earlier adapted variant.
  • Damnlie has shown interest but had to cancel
  • rad0 will build one and volunteered to document the whole process.
  • caduceus has shown interest but cancelled / doesn't reply to emails
  • rep will participate
  • jeroen has shown interest, but only in the delta robot, not the printing part
  • milo has shown interest but isn't sure yet
  • Mattronix will participate

Cost / Budget estimation

Here is an educated guess of what all the parts needed will cost, per printer...

4x stepper motors NEMA17:                           55
Controller board (Minitronics):                     79
Heated bed square PCB:                              23
Mk-7 filament drive gear:                            6
3x aluminum extrusions 1000mm                       60

Bowden version of E3D Hotend:                       70
(calculated as £55 == 64 euro plus shipping...)

Drive reels and rollers by Grabercars              100
(calculated as 118 US$ = 87 euro, minus discount, plus shipping, plus customs) 

Printed parts                                       30
(calculated as ~1kg per printer=22 euros. Plus electricity, plus failed prints...)

Round hardened glass bed 30cm (Blokker)              9
Aluminum actuator arms                               6 
Aluminum rods ("frame bracing")                     12
Power supply	                                    20
Spectra fishing filament                             5
Magnets and balls or ball joints, estimated         20
Different types of glue, heat-resistant and other   15

Misc: bolts, screws, microswitches, wiring,
 fans, connectors, all little stuff I forgot...     40

Grand total:                                       550

It should be well understood that changing or adding options like carbon fibre arms, different controllers, more hotends, different dimensions etc will drive the price up. But to the best of my knowledge, this bill of materials is complete for building a working complete printer, without compromising.

Please also note I did my best to estimate shipping and other fees correctly, but I cannot guarantee this will be 100% accurate. Maybe allow for a safety margin.

Timeline

I plan to place the order for the aluminum extrusions by Thursday November 7th, so I need to know the length everyone desires. Standard is 1000mm. I prefer ordering them cut, they can make much nicer cuts than we can, but mostly it helps with shipping; because 6 meter lenghts don't come by DHL...
In the mean time, a start should have been made with printing many of the base parts as shown in the pic. For 4 printers, we'd need 48 such parts, (plus a number of smaller parts). However, it has transpired that we need to have the aluminum extrusions to ascertain a good fit, before printing all parts.
Then to assemble and thread the towers, the only part(s) missing are the stepper motors. So by this time, we can either order the stepper motors, the stepper motors plus controller boards, or even ALL the remaining parts (extruder parts, hotends, heatbed etc.) So there is time until this step to choose hotend options, controller options, etc.

Nov 12, 2013: ordered 4 sets of aluminum extrusions, 1000mm
Nov 13, 2013: ordered a big quantity of thermal glue off DX to save some money...
Nov 18, 2013: ordered steel balls 10mm
Nov 20, 2013: ordered a heap of filament and a few stepper motors and controllers
Nov 23, 2013: ordered countersunk magnets via ebay...
Nov 24, 2013: finalize order from grabercars 

Testing the first printed parts

Today I printed a third arm, filed all three down a bit, removing debris and fit them together (a hammer and some careful use of it is required). It is a tiny bit too tight which is apparent by the somewhat wider gaps on the edges, but I think it still fits nice. It is very stiff and sturdy. Good.
20131011 232157.jpg

Better HotEnd

While looking for a solution to my ongoing extruder/hotend problems (it has skipping issues probably due to clogging) I at first wanted to purchase a better bowden connector with a pneufit, but soon after stumbled onto a modern and smart hotend design by E3D which offers a number of very clear advantages over my current J-Head;

  • Can sustain much higher temperatures because it has no PEEK or PTFE parts. Like over 300. Or even over 400.
  • Has no PTFE parts that can deteriorate, swell, leak, pinch or crush the filament, so probably more reliable.
  • Has instead of a power resistor a ceramic element which heats up extremely much faster.
  • Has a channeled fan casing/duct so the cooling isn't accomplished by accident, but with degrees of certainty.

And as far as I can see now, has just one drawback:

  • Has a mechanical weak point, so a head crash into the bed or something similar is really to be avoided at all cost.

I have been working on mounting it today but there was too much else to do plus my pneufit coupling went missing so that got delayed. And I need to adapt the holder because it doesn't fit this one as-is. And after that I need to change settings in firmware and in slic3r, and recalibrate the Z. But when done, I ought to have a better hotend which also has a much stronger pneufit bowden connector, which therefore permits the use of a stronger stepper motor, allowing higher feed rates thus feeding filament faster in a reliable way, which eventually will result in finally attaining the higher speeds these delta printers ought to be able to sustain (the platform being so lightweight). I hate it that I needed to severely limit my speed due to the extruder not being able to keep up. So I am very excited by this...

Sadly, my time is very limited this week due to personal reasons. Stay tuned for news later!
...

To cut a long story short: the new hotend is Fan-effing-tastic. Not only have all my extruder problems disappeared, but I was able to increase print speeds 220% (from 50 to 110) and as a bonus, I see no more stringing, as if by magic. This is the best return-on-investment I could ever have hoped for.

Small problem / minor setback

For my first printer I searched many shops to find a suitable round cheap glass bed. This proved rather hard to find. I finally got lucky in a Blokker store which sells a 30cm glass turntable for food serving purposes. Hardened glass, smooth edge, cheap: perfect. I bought two.. One spare. Now, I need to find a bunch more but... they no longer carry them. I visited 4 shops yesterday to no avail. Today, one which -upon inquiry with the manager- turned up two, stocked far away in the 'basement'. So, IF you happen to stumble onto one of these, do not hesitate and buy ! As of today, we need 2-3 more still... Update: I managed to get my hands on 3 more, so this has been addressed.

Extrusion profile

A week ago I found out the STL files of the parts that ought to fit 'around' the aluminum extrusions, didn't fit my current extrusions. I started looking into ways to change the STL files or find a different source for the extrusions. This proved hard, many vendors don't carry it, are unclear whether they carry it, or had extrusion profiles that were incompatible too, for various reasons. In the end however, I found out that my original source carries two variants of the 40x40 profile, and the second, thicker, heavier one does seem to fit our STL files... somewhat unexpectedly. So this ought to be fixed already. I've meticulously checked overlayed printouts of both items, and I feel confident it will fit inside. Otherwise, we could always still do some adjustments on the OpenSCAD files.

Big update

I wasn't happy with the prints we did; once the extrusions were there, we found that the braces need serious filing in the corners. I opted to adjust the corner radius in openscad, that ought to help. Secondly, the three tripods should fit together much easier, I also saw tolerances there that were unacceptable. I tried to recalibrate the slicer to make those errors diminish or disappear. We'll have to see.

Also, I finalized the number of participants, therefore the bill of materials. We started to order the first few things, either because time constraints force me to, or because we simply need them to proceed.

I had skipping or slipping in my left tower which destroyed a lot of prints, usually 80% through. This was getting to be a real problem; I managed to avoid this problem by bringing the speed down from 120 mm/s to 90 mm/s. But it merits future attention. At least now, the printer prints reliably again.

Having done some reading and research I felt the necessity to go for magnet-ball joints, so I ordered the magnets and balls. The shipping of such items can take many weeks, so I hope delays won't get too bad. We have as yet to find (or design) carriages and an actuator/platform that will fit those, but I feel confident that can be found, adapted or designed.